§ 20824 Water District Feasibility Review

Water Code·California
AI Summary·Official Text·Key Terms·Related Statutes·References
AI SummaryVerified

§ 20824 Water District Feasibility Review

Key Takeaways

  • •If the water department says there isn't enough water for a new project or the project won't work, the hearing about it gets delayed for up to two months.
  • •After two months, the project will be canceled unless one of two things happens:
  • •Either 75% of the landowners in the area ask the board to approve the project in writing,
  • •Or the board changes the project to match what the water department suggests.

Example

A group of farmers wants to create a new water district to get more water for their crops. The water department checks and says there isn't enough water for everyone in the proposed area.

The hearing about creating the new water district is delayed for two months. If, within those two months, at least 75% of the farmers (landowners) sign a petition asking for the project to go ahead, it might still happen. If not, the board might change the project to use less water, following the water department's advice. If neither happens, the project is canceled.

AI-generated — May contain errors. Not legal advice. Always verify source.

Official Source
View on CA.gov

§ 20824 Water District Feasibility Review

If the department reports within the specified time that the supply of water available for the use of the proposed district or that may be acquired by any practicable means, including the condemnation of existing rights, is not sufficient or that the project is not feasible for any other reason, the hearing of the petition shall be continued for not more than two months and shall then be dismissed unless within the period of the continuance either: (a) The board of supervisors is petitioned in writing by three-fourths of the holders of title to land to grant the petition. (b) The board of supervisors, if not so petitioned, modifies the project proposed in the petition to conform to the recommendations made by the department for the proposed district. (Added by Stats. 1943, Ch. 372.)

Last verified: January 23, 2026

Key Terms

water supplyprojectpetitionboard of supervisorsdepartment

Related Statutes

  • § 20820 Petition Filing Deadline
  • § 20821 Local Government Formation Notice
  • § 11290 Project Unit Expansion Authority
  • § 12664 Beach-Stone Lake Flood Control
  • § 20801 Petition Presentation Requirements

References

  • Official text at leginfo.legislature.ca.gov
  • California Legislature. Water Code. Section 20824.
View Official Source