§ 8414 Lien Enforcement Deadlines

Civil Code·California
AI Summary·Official Text·Key Terms·Related Statutes·References
AI SummaryVerified

§ 8414 Lien Enforcement Deadlines

Key Takeaways

  • •If you worked on a building or property but aren't the main contractor, you can ask for money if you weren't paid.
  • •You must ask for your money in writing (record a claim) before a certain time runs out.
  • •You have to ask before 90 days after the whole job is done, or before 30 days after the owner says the job is done (whichever comes first).
  • •If you wait too long, you can't ask for your money anymore.

Example

You helped build a house by painting the walls, but the main contractor didn't pay you.

You have to tell the owner in writing that you want your money before 90 days after the house is fully built. If the owner says the house is done and files a paper saying so, you only have 30 days to ask for your money. If you wait longer, you can't get your money.

AI-generated — May contain errors. Not legal advice. Always verify source.

Official Source
View on CA.gov

§ 8414 Lien Enforcement Deadlines

A claimant other than a direct contractor may not enforce a lien unless the claimant records a claim of lien within the following times: (a) After the claimant ceases to provide work. (b) Before the earlier of the following times: (1) Ninety days after completion of the work of improvement. (2) Thirty days after the owner records a notice of completion or cessation. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.)

Last verified: January 21, 2026

Key Terms

claimantdirect contractorclaim of lienwork of improvementnotice of completion or cessation

Related Statutes

  • § 8412 Contractor Lien Filing Deadlines
  • § 6660 Lien Notice To Members
  • § 9400 Contractor Funds Release Grounds
  • § 9408 Contractor Claim Rights Declaration
  • § 8400 Construction Lien Eligibility

References

  • Official text at leginfo.legislature.ca.gov
  • California Legislature. Civil Code. Section 8414.
View Official Source